TIC was awarded the contract for the construction of the Harleyville Plant modernization.
Scope of work consist of the construction of a new cement line designed to produce 3,000 TPD.
Technical Details
- One 196’ x 14’ diameter kiln driven by two 282 hp drives
- One finish mill
- One clinker cooler
- Four conveyor systems
- 10,000 cy of structural concrete
- 9,000 cy of preheater slip form concrete
- 4,600 tons of plate and ductwork
- 30,000 lf of pipe and 29,000 lf of cable tray
- 3,300 tons of steel