TIC was awarded the contract for the complete mechanical installations for Holnam’s Devil Slide Project that included a production line capacity increase from 1,100 STPD to 2,100 STPD of clinker.
Major systems and areas of work included the raw material crushing, storage and reclaim, raw mill feed and silo, baghouse, kiln feed, pre-heater and pre-calciner, clinker transport and coal systems as well as grate cooler and alkali bypass.